Council has approved an additional $150,000 for critical repairs to the Clohesy River Bridge on Barron Street, Koah.

Works will include:

  • Rectification of a sunken concrete abutment
  • Realignment of the bridge structure
  • Replacement of the timber deck and running planks

These essential works, identified through long-term monitoring, will ensure the ongoing safety and functionality of the bridge.

Works scheduled: Monday, 1 September 2025 – Thursday, 11 September 2025.

Bridge closed to all vehicular traffic during this time.

Pedestrian access will be maintained and temporary parking will be provided at both ends of the bridge.